On the evening of September 29, Neptune House in Jarboe Park filled with residents who came to hear what TriBridge wants to build at 500 Atlantic Blvd., the property most of us still call the old Kmart. According to the Beach Gazette's account of that meeting, the hotel rooms were not the main worry in the room. Water pressure for fire suppression was. People asked about the "big green monster," the 29-foot water tank that stands behind homes on Cherry Street.
Town Center West can't be built until someone solves fire-flow pressure at that end of Atlantic Boulevard. The solution the city and developer land on will also decide what happens to the tank. It could come down, it could be reconfigured to serve more buildings, or a second tank could go up beside it. The Community Development Board takes up the project on Wednesday, November 18.
What would replace the Kmart
Kmart closed in 2016. TriBridge Residential bought the property in 2019 through TBR Neptune Owner LLC, according to the Jax Daily Record. Under the current site plan, the Kmart portion of the strip center would be torn down. A three-story boutique hotel with 150 rooms would go up on the south side of the property, with a drop-off area. Two one-story restaurants would sit near the hotel, and two two-story buildings with retail and offices would run north to south along the central drive. The developer puts the cost at more than $100 million.
Managing partner Steve Broome told the September crowd that Sage Hospitality Group, which runs Dune House in Atlantic Beach, would operate the hotel. The project is being marketed as "Town Center West" because it's meant to send hotel guests toward the shops and restaurants of Beaches Town Center. As for dinner, the developer's attorney, Steve Diebenow, told the Jax Daily Record, "The community is advocating for a steak restaurant, so I have a feeling that that will be at the top of their target list, but there's no one that's been identified."
Publix stays put. The smaller-format store at 580 Atlantic Blvd., at the west end of the plaza, is a separate development. That Publix is also where the water story starts.
Why a 2022 tank sits at the center of a 2026 plan
A developer put up the green tank in December 2022 to give the new Publix enough pressure for its sprinkler system. Neptune's existing system couldn't supply that pressure then, and it can't supply what a hotel and two office-retail buildings would need now. "The water pressure that comes from the existing system isn't sufficient," Diebenow told the board in October, as the Beach Gazette reported.
Atlantic Beach's water system is right next door. The development team asked that city for a connection that would carry pressure for fire suppression only, with no drinking water, and Atlantic Beach said no. As Diebenow described them in the two Beach Gazette reports, the options are:
- Ask Atlantic Beach again once Neptune Beach approves a plan. The developer would pay for a pressure-only connection. Diebenow invited residents to come along when the team makes that request.
- Reconfigure the existing tank so it serves both Town Center West and the Publix at 580 Atlantic.
- Build a second tank.
Diebenow said neither tank option is the preferred solution. Broome described what the first option could lead to: "There is a path toward getting rid of the green monster. If water pressure becomes available, [the city of Neptune Beach] has to tap in and get rid of the green monster."
Neighbors behind the plaza care about the tank for reasons beyond how it looks. Residents told the Beach Gazette that they can hear the generator and pump at the existing tank inside their homes, often in the middle of the night. One resident said that at the HOA meeting, they were told another tank would be built if pressure couldn't be found, and that the City Council had already tried to work this out with Atlantic Beach. So the vote on the old Kmart is also a vote on the Cherry Street tank. Whatever fire-flow plan is approved will decide whether that block ends up with no tank, one tank serving more buildings or two tanks.
Wastewater is the second utility question. Diebenow said the city's treatment plant can handle 88,000 gallons a day and the project would generate 44,000. The existing lift station connection may not be big enough, though, so the route the wastewater takes to the plant is still being worked out.
The size rule a Walmart left behind
The board isn't voting on whether a hotel is allowed. Diebenow says the land use and zoning categories already permit a hotel, retail and offices by right. On November 18, the board will consider two variances from rules that are already on the books.
| Rule in Neptune Beach code | What Town Center West proposes |
|---|---|
| In the C-2 district, no retail store or freestanding building may exceed 60,000 square feet of gross floor area, and related buildings within 1,000 feet that operate as one business share the same combined limit | Two retail-office buildings of about 43,000 square feet each, plus the hotel |
| Buildings must occupy at least 70% of the applicable frontage | 45% of the frontage |
You can read the 60,000-square-foot cap in Section 27-237 of the city's Land Development Code. The frontage standard is in Section 27-236. The Beach Gazette reports that an earlier push to put a Walmart on this site never happened, but it led city officials to pass the 60,000-square-foot limit. That means the main hurdle for Town Center West is a rule that exists because of an earlier plan for the same property.
The site has seen other failed plans too. In August 2018, the City Council agreed with the board's recommendation and turned down a mixed-use special exception for 175 residences, up to 74 hotel rooms and 107,000 square feet of commercial space, News4JAX reported. In May 2019, the council approved Phase 1 of a new plan for the site, according to News4JAX. That plan was close to what's proposed today, and Diebenow told the board in October that it fell through.
This time, the team brought the council three concepts first: another big-box store, a hotel with townhomes, or an all-residential project. "We did not want to get into a protracted legal battle," Diebenow said at the September meeting. The plan now before the board combines pieces of all three.
Parking counts that don't match
The developer and city staff also disagree about parking. Community Development Director Heather Whitmore counted 148 spaces on the north side of the site and 138 on the south. Add about 100 shared spaces from Publix and the total comes to roughly 400. Staff says the project needs 463, which leaves it about 63 short. Diebenow says the developer's own analysis shows 105 spaces more than the code requires. He compared the site with the other side of Third Street, saying, "If you compare apples to apples, we have more spaces pro rata." City code allows shared off-site parking and valet, similar to what The Local and other restaurants nearby already use. Residents asked about a future parking garage, and Broome said the project doesn't create enough demand to need one.
What the homes behind the hotel have already changed
The hotel would back up to the Neptune by the Sea subdivision. Mayor Cori Bylund and that neighborhood's homeowners association organized the September meeting. Residents there raised concerns about balconies looking down into their backyards and about light, which they said was a problem back when Kmart was open. By October, the design had changed. "There will not be any balconies on the back of the building," Diebenow told the board. City staff now requires a photometric study to set acceptable lighting levels. Residents will be able to see the site's lighting plan, and the maximum height for the project is 35 feet.
The November date exists because the developer asked for more time. The October hearing was postponed at TriBridge's request, with guidance from staff. Board member Rene Atayan explained what the board is weighing:
"A lot of the things that are going to come up are going to be water and traffic. A lot of people don't recognize or appreciate the fact that we are a small barrier island. That is what we are. We cannot change that, and we have limited resources."
Dates on the calendar
- Wednesday, November 18: The Community Development Board considers the two variances and the preliminary development plan. The date is on the city's calendar. In the past, board agendas have listed 6 p.m. at City Hall, 116 First Street. The agenda will be posted on the city's CivicClerk portal.
- December 7 and 21: If the board approves the variances and the preliminary plan, the City Council will hold public meetings on the final development agreement, which sets a schedule for the infrastructure work, according to the Beach Gazette. The council's regular December meeting is Monday, December 7, at 6 p.m., per the 2026 schedule.
- After approvals: Diebenow estimates nine to 12 months of design and permitting before construction.
If the old Kmart and the Cherry Street tank are on your mind, whether you live nearby or are weighing a home within walking distance of Town Center, I'm glad to talk through what's proposed and keep you posted as the board and council act. Shelly Williford at Shell Sells FL follows these Beaches decisions closely. Let's Connect.